Stock quotes

Key indicators

50,000

Frequency in UES, Hz

86

%

Social Stability Index (SRS)

43,4

billion tenge

Net profit

35

billion tenge

The total volume of green bonds issued since December 2022

42,1

billion tenge

Dividends paid for 2023

395

VL

Overhead power lines

15

RES facilities

Commissioned in 2023, with a total capacity of 356,1 MW

83

ES

Electrical substations

222

power stations

Carry out the production of electrical energy in Kazakhstan

Chairmans Blog

Nabi Aitzhanov

Chairman of Management Board of Kazakhstan Electricity Grid Operating Company (KEGOC) JSC
Akmolinskiye MES
OHTL 4,230.431 km
10 SS 8,136.6 MVA
Aktyubinskiye MES
OHTL 1216,874 km
7 SS 2,425.5 MVA
Almatinskiye MES
OHTL 4216,900 km
12 SS 4957,2 MVA
Vostochnye MES
OHTL 1974,590 km
7 SS 4,362.5 MVA
Zapadnye MES
OHTL 2281,069 km
7 SS 1450 MVA
Sarbaiskiye MES
OHTL 2440,222 km
8 SS 6,569.9 MVA
Severnye MES
OHTL 3687,438 km
8 SS 3833,6 MVA
Tsentralnye MES
OHTL 3496,690 km
10 SS 3,741.6 MVA
Yuzhnye MES
OHTL 4263,240 km
14 SS 3635,7 MVA
Geography of activity
Aktyubinskiye MES Sarbaiskiye MES Akmolinskiye MES Severnye MES Vostochnye MES Zapadnye MES Tsentralnye MES Almatinskiye MES Yuzhnye MES

27 807,454

km
Overhead power lines

83

ES
With an installed transformer capacity of 39 112,6 MVA

Hotline